Malaysian Renovation / Construction Law |
How Does the Court of Appeal View
Debt Recovery Cases❓ Part 2
To make this case easier to understand, the facts are set out more clearly below.
Our client was one of the contractors in the project, responsible for a specific portion of the works. The dispute ultimately centred on two key issues:
📌 Whether the works were completed on time
📌 Whether the quality of the works met the required standard
Our Position: Completed on Time, Therefore Entitled to Final Payment
Our position was:
📌 The client completed the assigned works within the deadline given by the other party;
📌 Since the works were completed in accordance with the agreement, we are entitled to recover the remaining contract sum (final payment).
In other words, this is a typical dispute of: “Work completed, but final payment unpaid.”
The Opposing Party’s Position: Delay + Defects, Therefore No Payment and a Counterclaim
The opposing party took the opposite view, mainly on two grounds:
📌 (1) Alleged delay
They claimed that the works were not completed within the agreed timeframe.
📌 (2) Alleged defects / damage
They alleged that the works were defective, imperfect, or damaged, and that they had to engage a third-party contractor to carry out rectification works.
The key point is:
They claimed that the third-party rectification works incurred a substantial cost, which should be borne by our client.
As such, they not only refused to pay the final sum but also filed a counterclaim seeking a relatively large amount against our client.
What Are the Key Issues for the Court?
Such cases generally revolve around several core questions:
📌 What were the agreed timeline, scope, and standards?
📌 Was there actually a delay? Who caused it?
📌 Are the alleged defects or damages established? To what extent?
📌 Was engaging a third party necessary? Were the costs reasonable?
📌 Why was the final payment not made? Is there a valid basis for deduction or set-off?
In essence, the court looks at evidence and allocation of responsibility—not merely who “feels” the other party performed poorly.
If you are facing similar renovation or construction disputes, a practical reminder is:
The outcome often depends on whether documents, records, communications, inspections, and payment evidence are complete.
It is not just about whether you are right, but whether you can prove that you are right.







